Argentina redefines RIGI suppliers. In Brazil, Abeeólica seeks to halt battery auctions, Estadao reports.

In Argentina, foreign subsidiaries can qualify as suppliers under the Large Investment Incentive Regime (RIGI), EconoJournal reports; removal of the 20% local minimum is not established. In Brazil, wind association Abeeólica seeks to halt the December 2 and 4 auctions over cost allocation, Estadao reports; no injunction is reported. Luis Caputo confirmed approval for Argentina LNG's USD 50.75 billion plan through 2050, with conflicting accounts of formalization. TGS completed 50% of Argentina's Perito Moreno pipeline expansion, LMNeuquén reports; import savings depend on completing it. Infobae puts Argentina's country risk at 1,070 basis points, potentially raising financing costs. In Peru, Perupetro announced USD 718 million to reactivate Lot 192, without a detailed timetable or financing.


Global context

  • The US Department of State announced sanctions against Iranian regime insiders it accuses of profiting from stolen oil wealth; neither the measures nor those sanctioned are detailed.
  • The International Energy Agency (IEA) says Persian Gulf exports of refined products and LPG remain near half their pre-war levels.
  • According to the IEA, those disruptions weigh on global oil demand, while attacks on Russian energy infrastructure continue to restrict Russia's oil-product exports.

Main situations

Argentina redefines local RIGI suppliers through decree 1366/2026

Argentina formalized decree 1366/2026, which changes the implementing rules of the Large Investment Incentive Regime (RIGI) and the definition of a local supplier, according to Energía & Negocios. The publication recalled that the regime was approved with mandatory local-supplier participation of at least 20% in projects.

EconoJournal reported that the new definition allows foreign subsidiaries to compete as local suppliers. LMNeuquén added that the changes provide guarantees for purchases and sales of project stakes and facilitate foreign-exchange market access. Ambito also reported changes to share-sale and merger rules for RIGI beneficiaries, alongside foreign-exchange conditions. The sources do not describe the removal of the 20% local minimum.

What to watch

The admission of foreign subsidiaries as local suppliers in RIGI project procurement.

Brazil: Abeeólica seeks battery-auction halt, Estadao reports

Brazil's Associação Brasileira de Energia Eólica (Abeeólica) asked the Supreme Federal Court (STF) to suspend battery auctions scheduled for December 2 and 4, according to Estadao. The association filed a constitutional challenge to the section of Electricity Sector Modernization Law 15.269/2025 that requires only generating companies to share storage procurement costs.

Estadao reported that the action seeks an injunction suspending the provision and preventing its application in the auctions. The court requested information from the Presidency and National Congress within three days. The association had also filed a civil action to halt the auctions. eixos likewise reported the challenge to cost allocation; the reports do not say an injunction has been granted.

What to watch

An STF injunction decision on the cost-allocation rule and the December 2 and 4 auctions.

Argentina: Caputo announces RIGI approval for USD 50.75 billion LNG project

Luis Caputo confirmed that the Evaluation Committee of Argentina's Economy Ministry approved Argentina LNG's entry into the Large Investment Incentive Regime (RIGI), with planned spending of USD 50.75 billion through 2050. The developers are YPF, a majority state-owned oil company; Italy's Eni; and XRG, the international investment arm of the UAE's ADNOC.

Energía & Negocios reported that formalization through a resolution remained pending. EconoJournal, by contrast, described a resolution already enabling tax, customs and foreign-exchange benefits.

The governor of Neuquén, Argentina, Rolando Figueroa, announced that the final investment decision would be signed on November 30 in Buenos Aires, Argentina. According to Ambito, the project envisages 20,000 jobs and exports of 12 million tonnes of LNG. Infobae also reported plans for pipelines and processing plants.

What to watch

The official RIGI admission resolution and the signing of the final investment decision on November 30.

Argentina: LMNeuquén reports TGS completes 50% of Perito Moreno pipeline expansion

According to LMNeuquén, TGS, which is carrying out the Perito Moreno pipeline expansion in Argentina, completed 50% of the work and commissioned the first loop. These sections are pipes running parallel to existing ones. ADNSUR reported on November 19 that a loop had become operational the previous week.

LMNeuquén says the expansion will allow TGS to transfer 16 million cubic meters per day in winter to TGN, the intended recipient of those deliveries, and halve gas imports by ship. Those effects concern the expansion, not the loop already commissioned. The texts give neither a completion date nor the volume already flowing through the operational section.

What to watch

The daily volume actually transferred from TGS to TGN in winter.

Argentina: JP Morgan risk reaches 1,070 points, Infobae reports

After the 855 points reported by La Nacion at the start of the week, JP Morgan's country-risk indicator for Argentina reached 1,070 basis points, according to Infobae. The latter reported a jump of 135 points and a 13-month high. Another decline in bond prices accompanied the increase in the sovereign premium.

Infobae reported that Global bonds lost another 4.6% on Wall Street, the wholesale dollar advanced to $1,580 and the BCRA did not intervene in the market. In another report, it placed the retail dollar at $1,600 and Argentine equity losses at up to 10%. The publication also highlighted a $25 trillion maturity facing the Treasury.

What to watch

A Treasury notice explaining how it will cover the $25 trillion maturity.

Other developments

Peru: Perupetro announces USD 718 million to reactivate Lot 192

Perupetro announced planned investment of USD 718 million to reactivate and increase oil production at Lot 192 in Peru. The official announcement sets an amount and a production objective but does not identify investors or detail timing, financing or production targets.

What to watch

An investment breakdown and reactivation timetable for Lot 192.